Question: 1

How can material components be assigned to network activities?
Note: There are three (3) correct answers to this question.

A. By assigning them manually
B. Using the bill of materials transfer
C. Using assigned sales orders
D. Using ProMan
E. Using the Internet-based catalog

Answer: ABE

Question: 2

You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS). However, once you enter the WBS element and the working hours in CATS you receive an error message. What could be the reason?
Please choose the correct answer.

A. The system status created is active.
B. The system status master data locked is activate.
C. You are not the responsible person for that WBS element.
D. The confirmation exceeds the budget assigned to the WBS.

Answer: A

Question: 3

You want to extrapolate basic dates from lower to higher-level WBS elements. Which planning method do you choose?
Please choose the correct answer.

A. Bottom-up
...
... B. Strict bottom-up
C. Free planning
D. Top-down

Answer: A

Question: 4

You work with Project Builder (CJ20N) and want to use standard templates in your project structure. Which standard templates can you use?
Please choose the correct answer.

A. Standard time scheduling
B. Standard Bill of Material (BOM)
C. Standard cost planning
D. Standard Milestones

Answer: D

Question: 5

Your projects consist of WBS elements, several networks, and subnetworks. What are the advantages of new overall network scheduling (CN24N) instead of the old overall network scheduling (CN24)?
Note: There are three (3) correct answers to this question.

A. Scheduling of subnetworks and subordinate internal orders
B. Introduction of a configurable level concept for the targeted selection of subnetworks
C. Scheduling that takes available capacities and material availability into account
D. Improve performance through the targeted selection of subnetworks to be scheduled.
E. Detailed subnetwork monitor

Answer: BDE

Total Views: 610Word Count: 329See All articles From Author

Add Comment

Education Articles

1. Clat Coaching In Kolkata: Online And Classroom Learning Options Explained
Author: Amrita

2. Best School In Hosur
Author: sooraj

3. Revit Family Creation (working Professional / Intermediate)
Author: AEODC

4. Is Advanced Diploma In Finance Management Worth It For Working Professionals?
Author: INDIAN INSTITUTE OF BUSINESS MANAGEMENT & STUDIES

5. Nvq Level 7: Advancing Your Career In Health And Safety
Author: Gulf Academy Safety

6. Study Abroad In Dubai For Indian Students
Author: aaera

7. Best Consultancy In Hyderabad For Studying In Germany
Author: Krishna

8. Power Bi Course In Pune: Career Opportunities, Salaries, And Industry Demand
Author: meghana

9. Master Salesforce Devops Course | Online Training
Author: Vamsi Ulavapati

10. Why C And C++ Are Still Essential For Logic Building In 2026
Author: TCCI - Tririd Computer Coaching Institute

11. Azure Ai-102 Training | Azure Ai Training In Bangalore
Author: naveen

12. How Data Science Is Supporting More Effective Business Communication
Author: Arun

13. Best University In Delhi: Why Bennett University Is A Top Choice For Students
Author: Rohit Ridge

14. Best Mba In Finance Management – Build A Successful Career In The Financial World
Author: vishwavishwani

15. Navigating The Shift: Why Modern Public Projects Need Scaled Agile Expertise
Author: Passyourcert

Login To Account
Login Email:
Password:
Forgot Password?
New User?
Sign Up Newsletter
Email Address: