Question: 1

How can material components be assigned to network activities?
Note: There are three (3) correct answers to this question.

A. By assigning them manually
B. Using the bill of materials transfer
C. Using assigned sales orders
D. Using ProMan
E. Using the Internet-based catalog

Answer: ABE

Question: 2

You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS). However, once you enter the WBS element and the working hours in CATS you receive an error message. What could be the reason?
Please choose the correct answer.

A. The system status created is active.
B. The system status master data locked is activate.
C. You are not the responsible person for that WBS element.
D. The confirmation exceeds the budget assigned to the WBS.

Answer: A

Question: 3

You want to extrapolate basic dates from lower to higher-level WBS elements. Which planning method do you choose?
Please choose the correct answer.

A. Bottom-up
...
... B. Strict bottom-up
C. Free planning
D. Top-down

Answer: A

Question: 4

You work with Project Builder (CJ20N) and want to use standard templates in your project structure. Which standard templates can you use?
Please choose the correct answer.

A. Standard time scheduling
B. Standard Bill of Material (BOM)
C. Standard cost planning
D. Standard Milestones

Answer: D

Question: 5

Your projects consist of WBS elements, several networks, and subnetworks. What are the advantages of new overall network scheduling (CN24N) instead of the old overall network scheduling (CN24)?
Note: There are three (3) correct answers to this question.

A. Scheduling of subnetworks and subordinate internal orders
B. Introduction of a configurable level concept for the targeted selection of subnetworks
C. Scheduling that takes available capacities and material availability into account
D. Improve performance through the targeted selection of subnetworks to be scheduled.
E. Detailed subnetwork monitor

Answer: BDE

Total Views: 551Word Count: 329See All articles From Author

Add Comment

Education Articles

1. Hidden Data Jobs Market Growing Fast In Agra
Author: Dhanya

2. Sap Ariba Course | Sap Ariba Online Training In Hyderabad
Author: gollakalyan

3. Best Sap Training Institutes In Hyderabad Ameerpet
Author: naveen

4. The Ultimate Guide To Choosing The Best Sat Coaching In 2026
Author: rukhsar

5. Master Salesforce Data Cloud Course | Online Training
Author: Vamsi Ulavapati

6. Dynamics 365 Crm Course | Microsoft Dynamics Crm
Author: krishna

7. Skill-based Courses That Guarantee Job Placement
Author: UniversityGuru

8. Comptia Casp+ Certification: The Elite Path To Advanced Cybersecurity Mastery
Author: Passyourcert

9. Mbbs In Romania: Expert Guidance For Indian Students!
Author: Rajesh Jain

10. Comptia Security+ Certification: Your Launchpad Into The Cybersecurity Universe
Author: Passyourcert

11. Sap Abap Rap Course In Hyderabad | Sap Rap Training
Author: gollakalyan

12. Aima – The Smart Choice For A Reliable Management Aptitude Test
Author: Aima Courses

13. Data Engineering Training Institute In Bangalore – Master Real-world Data Skills With Ksr Datavision
Author: Ksr

14. Sap Btp Cap Course Online | Sap Fiori Online Training
Author: Visualpath

15. Advanced Multilevel Inverter Projects With Harmonic Reduction And Performance Analysis
Author: Kalyan

Login To Account
Login Email:
Password:
Forgot Password?
New User?
Sign Up Newsletter
Email Address: