Question: 1

How can material components be assigned to network activities?
Note: There are three (3) correct answers to this question.

A. By assigning them manually
B. Using the bill of materials transfer
C. Using assigned sales orders
D. Using ProMan
E. Using the Internet-based catalog

Answer: ABE

Question: 2

You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS). However, once you enter the WBS element and the working hours in CATS you receive an error message. What could be the reason?
Please choose the correct answer.

A. The system status created is active.
B. The system status master data locked is activate.
C. You are not the responsible person for that WBS element.
D. The confirmation exceeds the budget assigned to the WBS.

Answer: A

Question: 3

You want to extrapolate basic dates from lower to higher-level WBS elements. Which planning method do you choose?
Please choose the correct answer.

A. Bottom-up
...
... B. Strict bottom-up
C. Free planning
D. Top-down

Answer: A

Question: 4

You work with Project Builder (CJ20N) and want to use standard templates in your project structure. Which standard templates can you use?
Please choose the correct answer.

A. Standard time scheduling
B. Standard Bill of Material (BOM)
C. Standard cost planning
D. Standard Milestones

Answer: D

Question: 5

Your projects consist of WBS elements, several networks, and subnetworks. What are the advantages of new overall network scheduling (CN24N) instead of the old overall network scheduling (CN24)?
Note: There are three (3) correct answers to this question.

A. Scheduling of subnetworks and subordinate internal orders
B. Introduction of a configurable level concept for the targeted selection of subnetworks
C. Scheduling that takes available capacities and material availability into account
D. Improve performance through the targeted selection of subnetworks to be scheduled.
E. Detailed subnetwork monitor

Answer: BDE

Total Views: 540Word Count: 329See All articles From Author

Add Comment

Education Articles

1. Ai Stack Course | Ai Stack Online Training
Author: Hari

2. Sap Training Institutes In Hyderabad Ameerpet | Sap Datasphere
Author: naveen

3. Steps To Become A Python Developer
Author: Vinod

4. Secure Your Future: Understanding Sia Door Supervisor & Sia Trainer Qualifications
Author: mark

5. Unlock Your Teaching Potential: A Deep Dive Into Aet And Ctlls Qualifications
Author: Mark

6. Sign Up Now For Sap Cloud Platform Integration Training
Author: Pravin

7. L3: Assessor Understanding (taqa) Course & L2: Professional Taxi And Private Hire Driver Course
Author: Mark

8. L3: Award In Education & Training (aet) Course / L3: Teacher Training (ptlls) Course
Author: Mark

9. Dynamics 365 Crm Training: Microsoft Crm Course
Author: krishna

10. Salesforce Devops Training In Hyderabad | Visualpath
Author: Vamsi Ulavapati

11. Why Data Science Is Becoming Essential For Managers And Leaders
Author: Abijith

12. Azure Ai-102 Training | Azure Ai Training In Chennai
Author: naveen

13. Join Sap Artificial Intelligence Course Online At Visualpath
Author: Pravin

14. Sailpoint Online Course | Sailpoint Training In Ameerpet
Author: Visualpath

15. Mastering Project Schedules: The Ultimate Guide To Pmi-sp Certification
Author: NYTCC

Login To Account
Login Email:
Password:
Forgot Password?
New User?
Sign Up Newsletter
Email Address: