Question: 1
When considering risks, which describes an opportunity in a project?
A. An uncertain event that could have a negative impact on objectives
B. An uncertain event that could have a favourable impact on objectives
C. An event that has occurred resulting in a negative impact on objectives
D. An event that has occurred resulting in a favourable impact on objectives
Answer: B
Question: 2
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid,
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
Answer: C
Question: 3
Which may be funded from a risk budget?
A. Corrections due to off-specifications
B. Impact analysis of requests for change
C. Implementation of ...
... a fallback plan
D. Preparation of the Risk Management Strategy
Answer: C
Question: 4
What is the first task of product-based planning?
A. Produce the Initiation Stage Plan
B. Write the Project Product Description
C. Identify dependencies
D. Create the product breakdown structure
Answer: B
Question: 5
How many tasks does the product-based planning technique describe?
A. One
B. Two
C. Three
D. Four
Answer: D
Question: 6
Which is an objective of the quality review technique?
A. To identify a product's quality criteria
B. To provide assurance that the project is being conducted properly
C. To assess that a product conforms to set criteria
D. To ensure that staff are properly trained in the quality methods
Answer: C
Question: 7
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?
A. Risk category
B. Risk description
C. Risk response
D. Risk status
Answer: C
Question: 8
If an informal issue is defined as a problem or concern, where should it first be recorded?
A. Issue Register
B. Risk Register
C. Daily Log
D. Exception Report
Answer: C
Question: 9
Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project before the Project Board authorizes a project,
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
Answer: C
Question: 10
Which is the purpose of the Change theme?
A. Prevent change to baselined products
B. Identify, assess and control any potential and approved changes to baselined products
C. Establish mechanisms to monitor and compare actual achievements against those planned
D. Assess and control uncertainty
Answer: B
Question: 11
Why is a Project Brief produced?
A. To act as a trigger for the Starting up a Project process
B. To record the strategies and management controls to be used by a project
C. To provide a full and firm foundation for the initiation of a project
D. To be used by the Project Board as a basis for reviewing the progress of a project
Answer: C
Question: 12
Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations.
A. the measurement of benefits NOT yet realized
B. the handover of products
C. open issues and risks
D. the release of resources
Answer: C
Add Comment
Education Articles
1. Top-rated Digital Marketing Institute With Industry-focused ModulesAuthor: Career Boss Institute
2. Elite Site Reliability Engineering Training – Boosting Sre Course
Author: krishna
3. Azure Data Engineer Course In Ameerpet | At Visualpath
Author: gollakalyan
4. Ai & Machine Learning Course | Ai Ml Online Courses
Author: Hari
5. How Delhi Career Group Makes Nda Coaching In Bhopal A Success Story For Defence Aspirants
Author: Delhi Career Group
6. Gcp Cloud Data Engineer Training | Gcp Data Engineer
Author: naveen
7. Learn Advanced Javascript Frameworks (react) - Web Design Course
Author: TCCI - Tririd Computer Coaching Institute
8. Data Analyst Courses Iskcon Cross Road, Ahmedabad - Best Computer Institute
Author: TCCI - Tririd Computer Coaching Institute
9. Best Ai Course With Live Project Training - Tcci Institute
Author: TCCI - Tririd Computer Coaching Institute
10. Jesus Faith Antennas: How To Strengthen Your Spiritual Connection
Author: Alex Costa
11. Building Future Innovators: The Role Of Stem Centres & Partnerships
Author: stem-xpert
12. Sap Ariba Course And Live Sap Ariba Online Training
Author: krishna
13. The Joy Of Giving: How Festivals Teach Children Empathy And Gratitude
Author: Harshad Valia
14. The Essential Guide To The Aws Certified Sysops Administrator – Associate Certification
Author: Passyourcert
15. Boost Your Iq Score: Fast Learner Techniques Anyone Can Use
Author: Boost Your IQ Score: Fast Learner Techniques Anyon