Question: 1
You are a project manager in an organization that uses Microsoft PPM. You create a proposal for a new project by entering values for the Name, Description, Proposed Cost, Proposed Benefits, and Sponsor Name properties.
The PMO must be able to approve all project proposals that have a proposed cost above a certain threshold value.
You need to use a project approval workflow.
Which three objects should you use? Each correct answer presents part of the solution.
A. Project Departments
B. Enterprise Project types
C. Project Detail Pages
D. Project schedule templates
E. Phases and stages
Answer: BCE
Question: 2
You use Microsoft PPM to manage an e-commerce portal development program.
The program is separated into individual projects that represent each area of development. This allows each group to manage its own tasks while still having progress visibility at the program level.
You need to be able to see all programs and their associated individual projects from within Project Center.
What should you do?
A. ...
... Select the Enterprise Project Type Name field as the value for grouping.
B. Select the Master Program field as the value for filtering.
C. Select the Subprojects check box.
D. Select the Project Details view.
Answer: C
Question: 3
You are the Microsoft PPM administrator for a large company. The IT manager uses four business drivers for prioritization. The priority of all four drivers is set at 25 percent.
The IT manager adds an additional business driver that has a priority value set to 30 percent
You need to create a new prioritization that includes the additional business driver.
What should you do?
A. Create a new calculated prioritization. Select the drivers to priority.
B. Create a new manual prioritization. Select the correct department, and then select the drivers to prioritize.
C. Create a new manual prioritization. Select the drivers to prioritize, enter the value for each dnver, and then choose to normalize.
D. Create a new manual prioritization. Select the drivers to prioritize, and then rank the drivers sequentially.
Answer: A
Question: 4
You are using Microsoft PPM to manage an e-commerce portal development program. The program is separated into individual projects that represent each area of development.
You have the following requirements:
• All work and progress on individual projects must be reflected in the e-commerce portal development program.
• Each group must be able to manage their own tasks.
You need to set up the e-commerce portal development program and its associated projects in Microsoft PPM.
Where should you add resources?
A. in the e-commerce portal development program project site
B. in the individual project schedules
C. in Build Team, in the e-commerce portal development program schedule
D. in the individual project sites
Answer: C
Question: 5
Your organization is using Microsoft PPM to manage large projects. Within the Microsoft PPM environment you use SharePoint sites with task lists to manage smaller projects. You turn on the Timesheets feature.
You must collect information about the time that resources spend on all projects.
You need to ensure that you can capture timesheet data from the existing SharePoint task lists.
Which two actions will achieve the goal? Each correct answer presents a complete solution.
A. Convert the SharePoint task lists into an enterprise project.
B. Use the Get Started with Project Web App web part to add existing SharePoint task lists to Project Center.
C. Activate the enterprise project features for the SharePoint sites.
D. In Project Center, add existing SharePoint task lists to PWA as a project
E. In SharePoint, add existing SharePoint task lists to Project Center.
Answer: CE
Question: 6
You are a project manager using Microsoft PPM,
You need to create a new project that uses one of your company's templates.
What are two ways to achieve the goal? Each correct answer presents a complete solution.
A. From Microsoft Project, select Enterprise.
B. In Project Center, select New and then select the desired enterprise project type.
C. In Resource Center, select New.
D. From Microsoft Project select Featured.
Answer: AB
Add Comment
Education Articles
1. Master Asian Languages With Stanford Language Centre – Your Gateway To Learning Mandarin, Thai & Vietnamese In SingaporeAuthor: Mohammed Yusri
2. Azure Devsecops Training | Azure Devops Training In India
Author: visualpath
3. The Oracle Integration Cloud Training Hyderabad - Visualpath
Author: naveen
4. Sap Cpi Online Course | Sap Training At Visualpath
Author: gollakalyan
5. Social Media Marketing Basics: From Instagram Reels To Facebook Ads
Author: Shivam Kumar
6. Study Mbbs In Turkey: Top Universities, Costs, And Career Opportunities
Author: Mbbs Blog
7. Study Mbbs In Russia: A Top Choice For Indian Medical Aspirants
Author: Mbbs Blog
8. Community-driven Stem Centres: Empowering Local Innovation Through Partnerships
Author: stem-xpert
9. Bject-oriented Programming Made Easy With Java – Sssit Computer Education
Author: lakshmisssit
10. Shaping Young Minds At The Best Cbse School In Karunagappally
Author: Gregorios
11. D365 Online Training | Dynamics 365 Finance Operations
Author: Hari
12. All The Necessary Information That You Need To Know To Join Mbbs In Vietnam
Author: Mbbs Blog
13. Study Mbbs In Bosnia: Turn Your Dream Into Reality
Author: Mbbs Blog
14. Sleep Matters: The Science Behind Toddler Naps
Author: Kookaburra PreSchool
15. Top-rated Sre Training | Online Site Reliability Courses 2025
Author: krishna