Question: 1
In which situation is it required to update/change the cost baseline?
A. Roll-out delays affecting the original cost plan.
B. Change in subcontractor prices.
C. Scope changes supported by a legal binding document.
D. When a risk has materialized.
Answer: C
Question: 2
From which source should integration engineer resources be planned for the site integration to the radio network?
A. Include an estimation of local site solutions resources in the project headcount.
B. Prepare an RFQ for external suppliers with the support of Procurement.
C. Include the input from GNIC into your service cost estimation.
D. Communicate the need for integration engineers for your project during the EAC meeting.
Answer: C
Question: 3
How frequently is an update of the Cost Estimate at Completion required?
A. Each time there is a change in the scope of work.
B. Each time there is a change in the schedule or scope of work.
...
... C. At least once per month, prior to period end.
D. Every quarter before PRS (Profitability Reporting System) results are published.
Answer: C
Question: 4
Which of the following is a direct project cost?
A. Corporate office utilities.
B. Workers compensation insurance.
C. Installation materials.
D. Both corporate office utilities and workers compensation insurance.
Answer: C
Question: 5
What is the best timing to review the estimate at completion (EAC)?
A. Only during the planning phase, in order to anticipate all possible risks.
B. Only during project closure, in order to consistently explain the project results.
C. During the entire project lifecycle, at least once per month, and at every major change in scope.
D. Only when the project manager requests a review of the cost deviations.
Answer: C
Question: 6
What is the correct GIC to plan costs related to payment of a subcontractor responsible for BTS commissioning?
A. 7331 Implementation.
B. 7332 site acquisition.
C. 7348 project management.
D. 7333 construction works.
Answer: A
Question: 7
Which of the following inputs are used for Resource Planning?
A. Scope statement.
B. Resource pool description.
C. Historical information of resource utilization.
D. All of the other options.
Answer: D
Question: 8
What of the following cost components is NOT included in the CBL?
A. Non conformance costs.
B. Sub-contracting costs.
C. Risk contingency.
D. Base costs.
Answer: A
Question: 9
In which phase of the project is the greatest amount of its funding likely to be spent?
A. Initiating.
B. Executing.
C. Planning.
D. Closeout.
Answer: B
Question: 10
What is the relationship between actual cost, EAC and ETC?
A. Actual cost + EAC = ETC.
B. Actual cost - EAC = ETC.
C. EAC - actual cost = ETC.
D. ETC - actual cost = EAC.
Answer: C
Question: 11
What is the best demonstration that you are in control of your financial processes?
A. You can always explain the cost deviations.
B. You do not exceed the total CBL, even though some services business lines have exceeded their respective baselines.
C. There are no large deviations between forecast and actual costs.
D. You delegate completely to the project controller.
Answer: C
Question: 12
What approval process is required when the EAC deviates >2% from the CBL?
A. The CT starts the LoA approval process and if the LoA approves the cost increase, the initial CBL is updated.
B. The CT starts the LoA approval process and if the LoA approves the cost increase, the initial CBL is not updated, but the EAC will be updated to reflect the change.
C. The COM requests approval from CBC and if the CBC approves the cost increase, the initial CBL is not updated, but the EAC will be updated to reflect the change.
D. The COM requests approval from CBC and if the CBC approves the cost increase, the initial CBL is updated.
Answer: B
Question: 13
Continually measuring and monitoring the actual cost versus the budget is done to:
A. analyze the reasons for variances.
B. smooth out the variances.
C. approve the variances.
D. generate reports.
Answer: A
Question: 14
What activity is the final stage before input of the planned project costs to 4C?
A. Receipt of customer purchase orders.
B. Revision of the equipment delivery forecast.
C. Updates to the rollout schedule.
D. Joint analysis of the planned project costs by the project manager and cost and progress manager.
Answer: D
Question: 15
Your project is ongoing, all partner contracts have been renegotiated and new prices (higher by 8%) came into effect immediately. If all the other circumstances in your project remain unchanged, your CBL value will:
A. increase by 8%.
B. decrease by 8%.
C. not be affected by the change.
D. increase by a % dependent on project completion and other project costs.
Answer: C
Add Comment
Education Articles
1. Digital Marketing Course In Collaboration: A Smart Career ChoiceAuthor: Aima Courses
2. A Complete Guide To Osep Special Education Programs And Online Resources
Author: Passyourcert
3. Rcdd Certification Guide: Requirements, Exam, Cost, And A Practical Pass Strategy
Author: Passyourcert
4. Salesforce Devops Training In India | Online Course
Author: Vamsi Ulavapati
5. Smile Design In Chennai – Transform Your Smile With Advanced Cosmetic Dentistry
Author: ivar
6. Porcelain Veneers In Chennai Porcelain Veneers In Chennai – The Ideal Choice For A Radiant And Natural Smile
Author: ivar
7. Discover Your Path To A Safe Career With An Industrial Safety Courses
Author: Safety Isa
8. Best Saloon In Anna Nagar East – Professional Beauty And Grooming Services For Every Style
Author: MAHESH
9. Keratin Treatment In Anna Nagar – Get Smooth, Frizz-free, And Healthy Hair
Author: MAHESH
10. Us F-1 Visa Rejection 2026: Common Reasons & How To Avoid Them
Author: Nivesa EdTech
11. Non Invasive Hifu Face Lift In Anna Nagar – Lift And Tighten Your Skin Without Surgery
Author: MAHESH
12. How To Dominate The Cia Certification Exam: A Strategic Blueprint For It Professionals
Author: Passyourcert
13. Fpm Programmes At Mdi Gurgaon: A Pathway To Excellence In Management Research
Author: Rohit Ridge
14. Abacus Class Half Moon Bay | Build Strong Maths Skills With Sip Abacus
Author: SIP Abacus NZ
15. Train The Trainer For Security Industry: Skills, Qualifications & Opportunities
Author: Amba Training