In time management, very important concepts for pmp exam preparation are the tools and techniques for sequencing activities.
Tools and Techniques for Sequencing Activities
A manager can apply any one of several sequencing tools to organize and schedule their activities.
- Precedence Diagramming Method (PDM)
This technique uses an illustrative approach to sequencing activities that uses boxes and rectangles to represent each activity. The visual representation helps a project manager to see and connect activities by precedence. The activities are studied typically to determine the logical relationship and are connected to each other by arrows, flowing from left to right. This technique helps to identify those activities that must happen before others can begin or finish. This type of analyzing is called Critical Path Methodology (CPM). There are many dependency relationship types to employ when using PDM. PMP exam prep must include PDM.
Finish-to-Start (FS) type is the most common dependency, which begins an activity only when the one before it is complete.
Finish-to-Finish ...
... (FF) type allows completion of one activity based on the completion of the activity before it.
Start-to-Start (SS) type starts an activity based on the initiation of the activity before it.
Start-to-Finish (SF) type allows completion of an activity only when the activity before is initiated. This is the most rarely used method.
- Dependency Determination
Dependencies are situations that affect the sequencing of activities due to circumstances both internal and external to the project. Typically, a project manager may encounter three types of dependencies. PMP exam prep should detail:
Mandatory dependencies
Discretionary dependencies
External dependencies
- Applying Leads and Lags
These are techniques used to either start or delay an activity based on its relationship with the previous activity or predecessor. Since dependency deals specifically with the beginning or ending of an activity, leads and lags are methods to start or delay an activity before the actual predecessor activity is started or finished. For example, you can have two activities scheduled as a Finish-to-Start type dependency. Applying a lead to this could result in having the successor activity begin five days before the finish of the predecessor activity. PMP exam prep should include examples of leads and lags.
- Schedule Network Templates
Using templates helps to make sequencing activities faster, efficient and consistent. These templates can be used to illustrate all the project activities or divided into a sub network or fragment network. PMP exam preparation should include examples of the templates.
Kimberly Bloch, To Get the proper PMP exam preparation to pass the PMP exam prep with flying colors.Visit the site too for some useful hints on PMP preparation.
Add Comment
Education Articles
1. How Can Artificial Intelligence Transform Sap Sales Processes?Author: golla kalyan
2. Cloud Data Engineer Course | Google Data Engineer Course
Author: visualpath
3. Iapp Aigp Certification 2026: Exam, Passing Score, Cost, Training & Career Guide
Author: nytcc
4. Deepeval Agent Evaluation | Ai Agent Evaluation Course
Author: Vamsi Ulavapati
5. Understand Exactly What “placement Assistance” Means
Author: Avina Technologies
6. What Is Ecih Certification In 2026? Exam, Syllabus, Eligibility & Incident Response Guide
Author: passyourcert net
7. Interior Design Course In Noida – Build A Portfolio That Showcases Your Skills
Author: Manshi Kumar
8. Sap Datasphere Training And Sap Datasphere Course Online
Author: Subahan
9. What 1,286 Tutors Actually Charge For Home Tuition In Delhi Ncr (2026 Fee Study)
Author: EZ Tuitions Team
10. Protective Coatings For Tmt Bars: Improving Reinforcement Durability
Author: Ivar
11. Fiber-reinforced Concrete Additives: Strengthening Modern Construction
Author: Ivar
12. Rust-resistant Concrete Formulations: Improving Structural Durability
Author: Ivar
13. Polymer Based Cement Additives: Improving Modern Construction Materials
Author: Ivar
14. Understanding Echolalia In Children: Causes, Types, And Helpful Strategies
Author: Anima Mishra
15. Natural Crystals Explained: A Practical Guide For First-time Buyers
Author: Narendra Sharma