Question: 1

When considering risks, which describes an opportunity in a project?

A. An uncertain event that couldhave a negative impact on objectives
B. An uncertain event that could have a favourable impact on objectives
C. An event that has occurred resulting in a negative impact on objectives
D. An event that has occurred resulting in a favourable impact on objectives

Answer: B

Question: 2

Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.

A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true

Answer: C

Question: 3

Which may be funded from a risk budget?

A. Corrections due to off-specifications
B. Impact analysis of requests for change
C. ...
... Implementation of a fallback plan
D. Preparation of the Risk Management Strategy

Answer: C

Question: 4

What is the first task of product-based planning?

A. Produce the Initiation Stage Plan
B. Write the Project Product Description
C. Identify dependencies
D. Create the product breakdown structure

Answer: B

Question: 5

How many tasks does the product-based planning technique describe?

A. One
B. Two
C. Three
D. Four

Answer: D

Question: 6

Which is an objective of the quality review technique?

A. To identify a product's quality criteria
B. To provide assurance that the project is being conducted properly
C. To assess that a product conforms to set criteria
D. To ensure that staff are properly trained in the quality methods

Answer: C

Question: 7

Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

A. Risk category
B. Risk description
C. Risk response
D. Risk status

Answer: C

Question: 8

If an informal issue is defined as a problem or concern, where should it first be recorded?

A. Issue Register
B. Risk Register
C. Daily Log
D. Exception Report

Answer: C

Question: 9

Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists exists before the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project before the Project Board authorizes a project.

A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true

Answer: C

Question: 10

Which is the purpose of the Change theme?

A. Prevent change to baselined products
B. Identify, assess and control any potential and approved changes to baselined products
C. Establish mechanisms to monitor and compare actual achievements against those planned
D. Assess and control uncertainty

Answer: B

Question: 11

Why is a Project Brief produced?

A. To act as a trigger for the Starting up a Project process
B. To record the strategies andmanagement controls to be used by a project
C. To provide a full and firm foundation for the initiation of a project
D. To be used by the Project Board as a basis for reviewing the progress of a project

Answer: C

Question: 12

Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations.

A. the measurement of benefits NOT yet realized
B. the handover of products
C. open issues and risks
D. the release of resources

Answer: C

Question: 13

In what process is the authorization to deliver the project's products given?

A. Starting up a Project
B. Initiating a Project
C. Managing a Stage Boundary
D. Directing a Project

Answer: D

Question: 14

Which of the following is NOT part of quality planning?

A. Define quality responsibilities
B. Gain acceptance of the project product
C. Agree acceptance criteria
D. Set quality tolerances

Answer: B

Question: 15

Which should be provided by a project mandate?

A. Terms of reference
B. Detailed Business Case
C. Stage tolerances
D. Initiation Stage Plan

Answer: A

Question: 16

Which is an objective of the Starting up a Project process?

A. Identify who will be responsible for creating the Project Plan
B. Agree how the project will be monitored and controlled after initiation
C. Authorize the Project Manager to proceed with the initiation stage
D. Agree how issues and changes will be identified, assessed and controlled

Answer: A

Question: 17

Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project,

A. Management strategies
B. Plan
C. Stakeholder interests
D. Time-driven controls

Answer: B

Question: 18

If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?

A. Senior User
B. Executive
C. Corporate/programme management
D. Senior Supplier

Answer: C

Total Views: 515Word Count: 838See All articles From Author

Add Comment

Education Articles

1. Mastering The Ccie Wireless Certification In New York: Your Path To Networking Excellence
Author: NYTCC

2. Nebosh Course Requirements Decoded: Your Questions Answered
Author: Gulf Academy Safety

3. Top Ai Agents Online Course Training | At Visualpath
Author: gollakalyan

4. Agentic Ai Training | Agentic Ai Online Training
Author: Hari

5. Mlops Training In Hyderabad | Mlops Course
Author: visualpath

6. Master Your It Career: The Ultimate Guide To Ccnp Cloud Certification In New York
Author: NYTCC

7. Snowflake Data Engineering Course Online | Visualpath
Author: Visualpath

8. #1 Generative Ai Training In India | Online Training
Author: Pravin

9. Php Laravel Web Development Course: Tcci
Author: TCCI - Tririd Computer Coaching Institute

10. Explore The Online Advanced Diploma With 100+ Specializations In 2026
Author: UniversityGuru

11. Master Agentic Ai With Python At Tcci Tririd Computer Coaching Institute
Author: TCCI - Tririd Computer Coaching Institute

12. Data Science & Machine Learning Course: It Training Institute
Author: TCCI - Tririd Computer Coaching Institute

13. Clinical Research Courses: A Complete Guide To Building A Career In Clinical Research
Author: vaibhav

14. Transform Your Career With India's Premier Digital Marketing Training Program
Author: Aima Courses

15. Master The Google Cloud Architect Certification: Your Path To Professional Success
Author: Passyourcert

Login To Account
Login Email:
Password:
Forgot Password?
New User?
Sign Up Newsletter
Email Address: