Question: 1

Which of the following are prerequisites for business completion?(Choose two)

A. The order must have actual costs.
B. The order must be fully settled.
C. The balance of the order must be zero.
D. The order must have planned costs.

Answer: B,C

Question: 2

What information does the value category provide in the maintenance order?

A. The costs details for individual technical objects
B. The costs by work center
C. The material costs by valuation category
D. A summary of costs for multiple cost elements

Answer: D

Question: 3

Which of the following Customizing settings is required to assign a notification to a maintenance order operation?

A. Assignment of operations to all object list entries active
B. Assignment of order type to notification type
C. Maintain indicator for notification data on order header
D. Create default value profiles for general order data

Answer: A

Question: 4

When the user creates a maintenance ...
... plan for a call object (order), which value in the planning data determines the order type?

A. Priority
B. Maintenance activity type
C. Maintenance planner group
D. Main work center

Answer: C

Question: 5

A maintenance technician replaces a defective counter with a new counter.
Before the users can create a standard measuring document for the new counter, what step(s) must
they perform?

A. Create a new technical object to represent the new measuring point.
B. Create a special measuring document and set the Counter Replacement indicator.
C. Dismantle the old measuring point and create a new measuring point.
D. Create a new measuring point and change the measuring point from which the measurement reading was transferred.

Answer: B

Question: 6

A user has planned an operation with labor costs and material costs; however, the material
cost element is not assigned to a value category.
Where do the material costs appear in the value categories for the order?

A. In the overhead value category
B. In a new, automatically created value category
C. In the unassigned value category
D. In the internal activity value category

Answer: C

Question: 7

Which of the following always produces up-to-the-minute costing information for maintenance orders?

A. A standard analysis from the Plant Maintenance Information System (PMIS)
B. A standard query in SAP NetWeaver Business Warehouse
C. A maintenance order list
D. A shift report based on shift notes

Answer: C

Question: 8

Which task list can have both external and internal number assignment for the task list group number?

A. Bill of material task list
B. Equipment task list
C. General task list
D. Functional location task list

Answer: C

Question: 9

Which of the following is a function of deadline monitoring (transaction IP30)?

A. Generate a Logistics Information System (LIS) report for scheduled maintenance items within a specific period.
B. Convert maintenance notifications into maintenance orders within a specific period.
C. Convert maintenance calls into call objects within a specific period.
D. Generate a Logistics Information System (LIS) report for all overdue maintenance calls.

Answer: C

Question: 10

A maintenance plan has a completion requirement. The plan contains five maintenance
items that produce five notifications.
Which system status must each notification have before the maintenance call is completed and the
next maintenance call can be generated?


A. REL (Released)
B. ATCO (All Tasks Completed)
C. TECO (Technically Completed)
D. NOCO (Notification Completed)

Answer: D

More About the Author

yes, I am a Student and I am article author as well for CertsChief Network.

Total Views: 515Word Count: 611See All articles From Author

Add Comment

Education Articles

1. Write My Assignment
Author: Assignment Mentor UK

2. Diy, Robotics, And Innovation Kits — Building Tomorrow’s Innovators, One Project At A Time
Author: stem-xpert

3. How Ncrd Sims Mumbai Prepares Students For Industry 4.0 Careers
Author: Priya Roy

4. Guidewire Policycenter Training: Real-world Applications You Need To Know
Author: Yogesh Waran

5. Microsoft Dynamics 365 Training In Hyderabad | Finance Operations
Author: Hari

6. Top 5 Common Hipaa Violations And How To Avoid Them
Author: Prabhakar Pandey

7. How To Use Virtual Environments In Python Effectively
Author: lakshmimonopoly

8. Pgdm Colleges In Mumbai With Low Fees: Affordable Education For Your Bright Future
Author: Durgadevi Saraf Global Business School

9. Aws Devops Course Online | Devops Online Training
Author: Visualpath

10. Master Site Reliability Engineering Training Online Today
Author: krishna

11. Sap Papm Certification Course Online | Sap Papm Training
Author: naveen

12. The Future Of Itil: Trends To Watch In It Service Management
Author: Dorothy Benson

13. A Complete Guide To Tempering Chocolate Methods: Achieve Perfect Shine Every Time
Author: Candy DeSouza

14. A Complete Guide To The Best Schools In Jp Nagar: Top Choices For Your Child’s Future
Author: My School Admission

15. Building Emotional Intelligence In Early And Middle School Students
Author: Saurabh Singh

Login To Account
Login Email:
Password:
Forgot Password?
New User?
Sign Up Newsletter
Email Address: