Chhattisgarh Surguja Umpp 14th Time Unlucky

By Author: herbert carter
Total Articles: 10

Chhattisgarh Surguja Power Ltd’s efforts to find a developer have failed once again. The power company, a wholly owned subsidiary of Power Finance Corporation Ltd., has once again extended the last date for submission of response to global invitation floated to pre-qualify a developer for its proposed Chhattisgarh Surguja Ultra Mega Power Project (UMPP).

Poor response from the private developers has forced Chhattisgarh Surguja Power to postpone the submission date for the 14th time since it originally published the global invitation in March 2010. The RfQ is now slated to be opened on 3 October 2013.

Chhattisgarh Surguja Power plans to set up a 4,000 MW coal based power unit near Salka-Khameria villages at Udaypur tehsil in Surguja district of Chhattisgarh on BOO basis. The project will spread over 2,500 acre of land. Of the total required land, about 1,200 acre will utilised for setting up the power plant, 1,000 acre for ash dam, 200 acre for water conservation and 100 acre for developing a housing complex for staff members.
Private power developers’ interest in setting up UMPPs has waned in the recent years for several reasons. Non availability of land, coal linkage, rise in price of imported coal, non availability of equipments are some of the main project hurdles faced by power promoters.
As a result, of the total 16 UMPPs initiated by the government, only 4 UMPPs were handed over to private parties. Of this one, the Mundra UMPP has been completed and the other three are under various stages of implementation. The balance 12 UMPPs are still awaiting for developers.

UMPPs awaiting developers
Project Promoter Progress
Surguja UMPP Chhattisgarh Surguja Power Tendering stage
Sundergarh UMPP Orissa Integrated Power Tendering stage & awaiting environment clearance
Cheyyur UMPP Coastal Tamil Nadu Power Awaiting environment clearance
Tatiya Andhra UMPP Tatiya Andhra Mega Power Planning stage
Deoghar UMPP Deoghar Mega Power Awaiting environment clearance
Orissa UMPP (2) Sakhigopal Integrated Power Awaiting state government approval
Orissa UMPP (3) Ghogarpalli Integrated Power Co. Awaiting state government approval
Munge UMPP Coastal Maharashtra Mega Power Planning stage
Tadadi UMPP Coastal Karnataka Power Planning stage
Bihar UMPP Power Finance Corporation Location approved by CEA
Tamil Nadu UMPP (2) Power Finance Corporation Nascent
Gujarat UMPP (2) Power Finance Corporation Nascent

Total Views: 127Word Count: 333See All articles From Author

Investing / Finance Articles

1. Receive The Best Bookkeeping Service With The Help Of A Professional Bookkeeper Sunshine Coast
Author: Monique Bock

2. Bse Extended The Deadline For Mutual Funds Investors To Link Their Adhaar Card
Author: Robin Scott

3. How To Get Right Business Loan In Mumbai
Author: Amit

4. How To Identify Stocks Through Fundamental Analysis Of A Company?
Author: Chetan Rathod

5. How To Be A Successful Intraday Traders
Author: Robin Scott

6. Looking For A Business Loan – Heard About Loan Against Property And Loan Against Bonds?
Author: Chetan Rathod

7. Why It Is Important To Diversify Your Investments
Author: money classic research

8. Some Devious Tricks To Win The Stock Market
Author: Robin Scott

9. Finance Your Mobile With 0 Percent Interest Loan
Author: Meenal Wahi

10. Mcx Free Tips And Nifty Option Tips – All In Accurate Way To Gain More Profits
Author: Sandy Allen

11. 5 Simple Hacks For Reducing Ac Repair Cost
Author: Rajesh Patil

12. Advantages Of Payday Loans
Author: Broad Stevens

13. Seeking For Huge Returns? – Know The Top Penny Stocks For 2018 India
Author: Robin Schott

14. Challenges Faced During Merger And Acquisitions By Firms
Author: Sandeep Sharma

15. Why It Is Important To Understand Your Risk Tolerance
Author: Robin Schott

Login To Account
Login Email:
Password:
Forgot Password?
New User?
Sign Up Newsletter
Email Address: